| Project Phase | Consultant / Contractor | % Complete |
| Design: | Point Engineers | 0% |
| Construction: | | 0% |
Project Description
This project provides for the coordination with adjacent propoerty owners, public involvement, design, temporary construction easement (TCE) acquisition, utility coordination, utility relocation, construction, and construction administration for the building of a Westfield Estates Unit 9 sound wall. This wall extends approximately 400 linear feet westerly along the PUSD storm water basin south boundary from the L101 right-of-way to 95th Avenue. This project will likely include the processing of utility agreements (APS, SRP, COX, Qwest/Centurylink, SWG, etc) for design and construction and developmenment and intergovernmental agreements.
Project Status
6/5/2013 - Noise Analyses is being finalized to determine the length and height of the wall along the southern boundary of Sun Valley Elementary School
Latest Public Engagement
7/2/2012 - Meeting with the School District prior to construction in the Fall 2012. |