| Project Phase | Consultant / Contractor | % Complete |
| Design: | EPS Group, Inc | 100% |
| Construction: | Nesbitt Contracting Co. | 95% |
Project Description
This project will provide for the design, right of way acquisition, utility relocations, extensions, and burying overhead power lines as determined, construction/reconstruction, and construction administration of the 83rd Av street widening to two lanes each direction with bike lanes and raised landscape median. Improvements include street lighting, water lines, storm drain, utility sleeves and ITS improvements from Butler Dr to Mountain View Rd. Also included are the north half-street improvements on Butler Dr from 83rd Av to 79th Av adjacent to Pioneer Community Park (CS00034).
Project Status
4/30/2013 - Project is nearing final construction completion. Final paving, landscaping, and irrigation will continue through May and into early June 2013. Community Park improvements will continue through summer 2013.
Latest Public Engagement
4/30/2013 - Construction Hotline (1-877-349-1433) is provided for questions or comments regarding the construction activities of this project. |