| Project Phase | Consultant / Contractor | % Complete |
| Design: | EPS Group, Inc | 95% |
| Construction: | TBD | 1% |
Project Description
This project provides for public involvement, design, ROW acquisition, agency and stakeholder coordination, utility relocation, extension and burying overhead facilities as determined, materials testing, construction and construction administration of the selected truck road reliever to be constructed in the NW portion of the City. Improvements will include one lane in each direction, intersection improvements at Rose Garden Ln and Pinnacle Peak Rd, signal construction at 107th Ave and Pinnacle Peak Rd. This project will likely include processing of utility agreements (APS, SRP, COX, Qwest/Centurylink, SWG, EPNG, etc) for design and construction, development agreement and intergovernmental agreements.
Project Status
5/1/2013 - APS finalized the poles relocations adjacent to the Agua Fria. The Truck Road will be advertised for construction in May.
Latest Public Engagement
5/1/2013 - A public meeting will be scheduled when the contractor has been awarded the construction contact. |